The 2015/2016 season short chrono

20.07.2015 – The magnetic measurements of BEP magnets are finished.
08.10.2015 – BEP magnets are assembled at site.
23.12.2015 – Vacuum of 10-6 Pa is pumped at BEP.
16.01.2016 – BEP is fully assembled, powered and ready for beam
27.01.2016 – First е- captured to BEP (at 390 MeV)!
16.02.2016 – Beam current achieved 500 mA at BEP during beam scrubbing.
21.03.2016 – The BEP-VEPP transfer channel assembly is finished.
22.03.2016 – Beam extracted from BEP.
22.04.2016 – е- beam captured to VEPP-2000 ("warm mode")!
26.04.2016 – Pulsed orbit bumping system at BEP started operation.
27.04.2016 – VEPP energy set at 510 MeV.
31.05.2016 – е- current at VEPP achieved 430 мА during beam scrubbing.
23.06.2016 – First е+ captured to BEP!
28.06.2016 – е+ beam extracted from BEP.
30.06.2016 – е+ beam captured to VEPP-2000!
05.07.2016 – е+ current achieved 170 mA at VEPP-2000.
19.07.2016 – two test beams of low intensity at VEPP-2000 ("warm mode").
21.07.2016 – Low intensive beam accelerated to 997 MeV at BEP. е- beam extracted from BEP at the energy of 980 MeV.
29.07.2016 – The complex stopped for summer shutdown.