Towards beam arrival

In September all the BEP quads were coupled into doublets, precisely aligned and doweled. In October the magnetic system was assembled at the booster hall and geodesicaly aligned. The vasuum system assembly started. In parallel the K-500 transfer channel was finished. The vacuum was obtained in the middle of December. Minor works of busbars connection and water cooling circuit assembly remains, BEP booster is close to completion.