K-500 assembly approaches to completion

Final part of K-500 e+e- beams transportation channel from new injection complex to VEPP-2000 complex is near to completion. In the BEP hall all K-500 magnetic elements are installed. The vacuum system assembly of the rising section is in progress.
At the same time the portion of 5 D-quads of booster synchrotron was obtained from BINP workshop and passed through magnetic measurements. Final batch of 6 quads is still under upgrade. Two pulsed dipole magnets (so called BUMP-magnets) are recieved. These novel magnets will be installed at BEP to produce closed orbit distortion before beam extraction that is essential at the top energy with the existing rather weak kickers.